Capital South Campus Center Report

Last activities reported 7/18/13

  • Piles and concrete pile caps complete, gravel placement to bottom of grade beam elevation in progress

 

Work Completed 7/18/13 through 8/19/13

  • Concrete grade beam are 100% complete
  • Perimeter foundation walls are complete and waterproofing membrane applied
  • Leveling plates for steel columns are placed
  • Compacted fill between grade beams is complete

 

Youth Build

  • Youth build program continued on a weekly basis on site and classroom. Included was a short classroom session by Omni Development on construction management.
  • A field trip to Reo Welding was conducted on August 13th. Students observed project steel fabrication and the use of computer aided fabrication machinery. Bob Reo explained and demonstrated the process from drawings to finish fabricated steel.
  • Future field trips are scheduled for a testing lab, concrete batch plant and steel reinforcing fabrication shop.

 

Short term schedule

  • Foundations and partial backfill is complete and ready for steel erection
  • Steel fabrication is scheduled to start Wed Aug 21st and weather permitting, complete in 1 week.
  • As soon as sufficient steel is erected to support foundation walls, exterior fill operations will continue.

 

Final Completion

  • On track for June 13, 2014
 